|
|
Navigating Bends in Alabama
Swampland by Paul Miller |
 |
| INROCK's Jay
Miller uses an EDM transit to verify the
pipeline route in order to optimize the plan of
the
drillpath. | | When
the Alabama Gas Corp. gas utility Alagasco needed to
complete a 10-in. gas distribution pipeline under the
Autagua Creek at Booth, Ala., it discovered a maze of
obstacles in a severely restricted right-of-way to make
any driller’s life miserable.
The
site lay more within swamp wetlands than under the
creek, The drill-path also crossed under a railroad.
However, the pipeline corridor allowed only 10 to 15 ft.
either way of the centerline. In addition, the design
called for five PIs (points of intersection or bends) in
the profile of the pipeline.
 |
| Gary Moberley calibrates the
steering tool interface which sends navigational
data to the
driller. | | When
Sunland Construction Co. Inc. of Eunice, La., received
the original pipeline project, it was designed for
open-cut construction. Site problems led both Sunland
and Alagasco to consider an alternative proposal to
install the pipeline by directional
drilling.
James
Daigle, vice president of Sunland Construction, said
they called on the navigation services of INROCK®
Guidance Systems Inc.,
Houston, to assist in the pipeline project. With the
expertise of Jay miller from INROCK®,
Sunland was able to smooth the bends and negotiate a
successful crossing with a single horizontal curve in
the pipeline design. The overall length of the crossing
was 2,170 ft.
Tommy Taylor was the Alagasco project manager for
the Autagua crossing. Taylor said the pipeline corridor
included archaeological sites regarded as "got spots,"
that would have required separate excavations and
sifting. This additional work could have delayed the
project which was to serve an industrial customer, and
also would have resulted in about $200,000 in additional
costs. The wetlands also gave both the owner and
contractor cause for sensitivity in handling the
environment.
 |
| Sunland's directional drill
rig begins the hole-opening phase of the
drilling
operations. | |
Miller began the survey process by completing a
thorough survey of the pipeline route. Using a land
survey transit with an electronic
distance measuring (EDM) instrument, Miller verified
the route, establishing precise locations of the points
of restriction in relation to the planned location of
the drilling rig.
With the survey completed, Miller was able to map
out an alternative pipeline route that eliminated all
but one of the PIs. It required a sharp horizontal turn
in order to meet tie-ins required for the
pipeline.
Sunland deployed an HDD rig with 475,000 lbs of
thrust and pullback capacity for the Autagua crossing.
The rack-and-pinion drill rig was custom designed and
built by Sunland’s drilling superintendent Butch Kabala.
Soils encountered at the drill site included sand, pea
gravel and clay. Sunland used bentonite and mud-handling
equipment supplied by Parchem for the project.
In guiding the drilling process, INROCK® employed a
steering tool system with Tracking abilities to provide continuous navigation
data. The steering
tool is situated downhole in non-magnetic collars
behind the motor
or jetting
assembly and transmits data to the interface unit
via a single conductor wire. The information is sent to
the driller’s console so that constant drill head
positioning can be maintained. The tracking
grid system aids in determining accurate horizontal
location at the launch and exit points of the
drill.
 |
| INROCK's
steering tool system provides continuous updates
for the drilling
navigator. | | Sunland began the horizontal curve at 1,061 ft
from the entry point just short of the midpoint of the
bore. The design called for a 4.5 degree curve to the
left. "We planned the curve to allow a stress factor
that was very acceptable," said Miller, "We kept it well
in excess of the bend capacities of the product
pipe."
Miller identified critical elements in
constructing a directionally drilled crossing with
horizontal curves. "One item often overlooked is the
additional stress induced in the pipeline through the
sections of the borehole in which you are building angle
and turning at the same time," explained Miller. He said
the typical rule is to use a bend radius of 100 times
the pipe diameter. Several special formulas and
calculations are also used in the design considerations
as well as the guidance and tracking, said
Miller.
Daigle said they were able to take the drilled
crossing on a long slow radius which minimized the
pipeline stress. The crossing proceeded without incident
and the pipeline was tied in
successfully.
"The precise navigation services were certainly
essential in ensuring the success of the crossing." said
Daigle. | Back To
All Editorials
>>>
EDITORIALS
•• CONTACT US
•• INROCK®
HOME
DRILLING SYSTEMS ••
GUIDANCE
SYSTEMS •• EQUIPMENT
SYSTEMS •• DRILLING
FLUIDS
 U.S.A. • Toll Free: (877)2 INROCK • Tel:
(713)690.5600 • Fax: (713)690.8300 Europe • Tel:
(+44)1273.735.500 • Fax:
(+44)1273.735.511
| | |
 |
|
OUR
COMPANIES |
|
|
|
NAVIGATION |
|
|
|
CONTACT US |
|
Contact
Form Use our
simple to use Contact Form to
receive a detailed response.
ABOUT
US
EMAIL
US Click
here for our
list of our company email addresses listed at the bottom of our Contact
page
CALL US TODAY Call today
to talk one on one with our professional and knowledgeable staff.
U.S.A. Toll
Free: (877)2 INROCK Tel: (713)690.5600
EUROPE TEL: #44.1273.735.500
|
| INROCK®
PRODUCT SHEETS |
| Click
here to go to
our Company Download Area to download product sheets from all of our
companies. | |